Learn · Value stream mapping
Creating a value stream map
A value stream map shows on one sheet how a product flows through your production — and how much of the lead time actually adds value. Usually it is a small fraction. This page explains the procedure without prior knowledge.
What is a value stream map?
The method comes from lean management and was made known by Mike Rother and John Shook (“Learning to See”). It draws the path of a product family from raw material to customer: each process as a box, each inventory in between as a triangle, and on top the information flow from order to work order. In Taktane the information flow is blue: electronic as a zigzag, manual as a straight arrow, each labelled with content and rhythm (“Forecast · monthly”).
Below the drawing is the timeline: waiting times in inventories on top, processing times below. Their ratio — the value-added ratio — is below 5 % in many plants. That is exactly what the analysis makes visible.
When does it pay off?
- Delivery times are much longer than the pure processing time.
- Large inventories sit between processes and nobody knows exactly why.
- Before investing in a new machine: is it really the bottleneck?
- When several departments work on one product and blame each other for delays.
In six steps
- 1
Choose a product family
Products that largely go through the same processes. One map for everything at once becomes unreadable.
- 2
Determine customer demand and takt time
How much does the customer need per day? Takt time = available time ÷ customer demand. It is the yardstick for every process.
- 3
Record the processes on site
Measure at the workstation, don't estimate at the desk: cycle time, changeover time, OEE, number of operators, shifts. The data sheet helps.
- 4
Count inventories
What lies between the processes, in pieces. Inventory and daily demand give the waiting time.
- 5
Calculate lead time and value-added ratio
The sum of waiting and processing times is the lead time. The share of processing time in it is the value-added ratio.
- 6
Design the future state
Along the eight questions by Rother and Shook: where can it flow, where does it need a supermarket, which process sets the pace? This becomes an action plan.
The key figures
- Takt time: how often the customer needs a part — the yardstick.
- Cycle time: how long a process takes for one part. Above takt time, the process is a bottleneck.
- Lead time: how long a part takes from receipt to shipping, mostly waiting time.
- Value-added ratio: processing time ÷ lead time.
- OEE: how much of the planned time a machine actually produces good parts.
Common mistakes
- Average values from the system instead of times measured on site.
- Inventories estimated instead of counted — they make up most of the lead time.
- Confusing takt time and cycle time.
- A future state without measures, owners and dates remains a nice picture.
How Taktane helps
- Every figure shows its calculation with the values used.
- A method check warns when the value stream looks good but is methodically wrong.
- Future states are separate scenarios and can be compared with the current state figure by figure.
- Presentation mode for the workshop and a printable summary afterwards.
For recording on site there is a printable data sheet with measuring instructions. View data sheet →