Capacity management is a standalone module: a line exists independently of whether a value stream is ever drawn for it. This guide walks through the full path, from the first line to comparing forecast against actual work.
Create a line
A workstation or production line, e.g. "Turning" — organization-wide, under capacity management, not tied to a single project.
Enter master data
Cycle time (minutes per piece), operator count, OEE (%), and shift model (1/2/3-shift) — the same figures as a VSM process box, but maintained independently of it here.
Enter monthly demand
Twelve values, one field per month. Optionally add a stress test (e.g. demand × 1.2) for an upside scenario.
Read the traffic light
Load rate = demand ÷ capacity, calculated automatically per month. Blue/green/orange/red show how tight the line is — the recommended action matches the color automatically.
Add actual hours
Once a month is closed: how many hours this line actually worked — in hours, not pieces, because a line can serve several product variants with different cycle times.
Compare forecast vs. actual
The line's chart shows required hours from the demand forecast, available hours from the shift model, and the actual hours entered, side by side — making it visible whether a year is tracking to plan.
Track actions
For each line: description, owner, due date, and optionally a target month — typically created as soon as a traffic light turns orange or red.
🔵 Underutilised (< 0.5) · 🟢 Ok (0.5–1.0) · 🟠 At risk (> 1.0–1.2) · 🔴 Overloaded (> 1.2)
Try it yourself
Capacity management is part of every Taktane account, whether or not a value stream exists yet.